with a request body that specifies how to map the columns of your import file to the associated CRM properties in HubSpot.... In the request JSON, define the import file details, including mapping the spreadsheet's columns to HubSpot data. Your request JSON should include the following fields:... entry for each column.
Lidl RDC, Newbridge, Ireland
The Project
Slab depths varied from 200mm to 300mm to suit different load requirements from the client. The construction included 2 layer slabs (separated by high-density insulation layers) for the new freezer area and also under a potential future freezer area.
Our Approach
The 60,100m2 slab was constructed over 46 pouring days over 4 phases of work to fit in with the progress of steelwork, roofing and cladding on the site. A lot of the slab area included underfloor heating pipework, therefore Twintec worked closely with the main contractor to manage their works alongside this.
Twinted were selected to construct the 60,100m2 floor slab for Lidl's new distribution centre in Newbridge, Ireland.
Request for a Copy
Once you click ‘request’ below you will be redirected to page where you can save the .pdf document to your PC.